increasing the current in the storage ring

Another goal has been reach in this commissioning. Only 8 days after this tests start we have up to 4 mA average current in the beam of the storage ring. The transmission from the booster ring to the storage looks good with values close to the 100%.

Also the beam is stored in this ring for hours now, and it's time to start accumulating charge in this storage.

It looks possible that at the end of this week one frontend shutter would be open and start seeing synchrotron light in the first beamline.

update: Looking on the ccd acquisition, I'm counting up to 5 different clients looking images of the diagnostics beamline. The peak was this morning about 10 computers looking on the same camera (I cannot count the number of persons looking this computers).